Optimising cost and value.

Whether reuse makes sense in any given place depends on two things: how much it costs to deliver the water, and how much that water — and anything recovered with it — is worth.

Cost of infrastructure

What it takes to deliver the water

Extent

How much new infrastructure is needed

Complexity

How clean the water must be made

Value of the product

What the water (and recovery) is worth

End use

What the water replaces or supplies

Recovery

Energy, nutrients and minerals

Reuse is attractive when value exceeds cost.

The cost spread

The outrageous range of reuse costs.

Differences in the scope and complexity of projects mean that there is a three orders of magnitude difference in the per cubic metre of product water cost of water reuse projects. Geography explains a lot of these differences: labour costs and permitting requirements are lower in some countries than others. Extent and complexity explain the other costs. In some cases a reuse project may involve no more than directing a pipe into an irrigation canal. In others it might involve multiple advanced oxidation processes and long distance conveyances.

US$ per m³/day capacity$0$10,000$20,000$30,000$40,000$50,000USA52 projectsMedian $8,800Other high income23 projectsMedian $3,800Other middle income21 projectsMedian $1,300India51 projectsMedian $360

Boxes show interquartile range (25th to 75th percentile); thick line is the median. Whiskers extend to 1.5 × IQR; dots are outliers beyond.

Source: GWI Reuse Project Tracker; excludes China.

Industrial reuse economics

Industrial reuse economics

On-site industrial water reuse enjoys a much lower standard deviation in unit cost than municipal reuse systems, but the economics of water reuse in industry is much more complex. It is inextricable from overall production economics. It is also complicated by regulation. The more times water is used in a plant the more contaminants are likely to build up (reducing process efficiency), but the more contaminated a wastewater stream becomes, the more troublesome it is to dispose of. It leads to the “dilute to pollute” phenomenon whereby it is often cheaper to dilute a waste stream with water to within permitted limits than to save the water and produce a concentrated waste stream that might violate regulations. Changing the economics of industrial water reuse will involve improving the economics of treatment and finding more value in waste streams as an alternative to disposal.

What goes into the cost

The anatomy of a reuse project cost.

The six stages of the treatment train are where project-to-project variation lives. Some projects need every stage built from scratch; others need just one. Within each stage, the technology chosen can swing the cost by an order of magnitude.

Total project cost

Construction

The treatment train and pipes

Non-construction

Soft costs and finance

Water reuse infrastructure

Collection

Sewers, pump stations, lift stations

Primary

Screening, grit removal, sedimentation

Secondary

Biological treatment, clarification

Disinfection

Basic pathogen removal

Polishing

Advanced treatment to spec

Distribution

Pipes, pumps, storage, conveyances

Polishing technology options

used in combination, depending on end use

Ultrafiltration
Reverse osmosis
Activated carbon
Ion exchange
Other filtration
UV
Ozone
Other AOPs

Other value recovery

value pulled out alongside the water

Sludge

Processing and energy recovery

Nutrients

Removal and recovery

Materials

Other value recovery

Non-construction costs

  • Project development
  • Planning
  • Design
  • Permitting
  • Public outreach
  • Insurance
  • Project management
  • Contractor overhead & profit

Financing costs

  • Capital amortisation
  • Interest cost

Often the largest line item

Construction
Polishing (subdivided)
Non-construction

Variation comes from which stages are built, and how far the polishing has to go.

Case study

Napa Purified Water — two alternatives at 10 MGD.

The Napa Sanitation District's potable reuse feasibility study (Carollo) is one of the few public DPR programmes with a fully itemised cost stack. Both delivery alternatives share the same 37,850 m³/d advanced water purification facility — only the conveyance and storage infrastructure changes. It is the clearest available view of where treatment money actually goes.

Alt 3 — Treated water augmentation

$7,136 per m³/day

Treatment
$6,251
Infra
$885

Alt 6 — Raw water augmentation

$7,919 per m³/day

Treatment
$6,251
Infra
$1,668

Napa treatment breakdown — same for both alternatives ($6,251 per m³/day)

RO
$1,929
MF/UF
$1,242
UV
$819
Chem
$740
Resid
$634
Bldgs
$887

Treatment unit-process splits estimated from comparable California DPR studies; neither project publishes a public itemised breakdown of the sub-processes within the AWPF.

Source: Napa Sanitation District Potable Reuse Feasibility Study (Carollo). Costs in USD per m³/day of installed capacity.

Case study

Pure Water Southern California — anatomy of a $9 billion programme.

The Metropolitan Water District of Southern California and Los Angeles County Sanitation Districts' Pure Water Southern California (PWSC) project is one of the world's largest planned potable reuse schemes — roughly 150 MGD (568,000 m³/day) of purified water for groundwater recharge and indirect potable reuse.

Capacity

~568,000 m³/d

150 MGD at full build-out

Total project cost

~$9 billion

Range $8–10 bn

Unit cost

~$15,800

per m³/day capacity

Composition

Breakdown ($4.5bn treatment)

indicative split — see footnote

RO
$1.10bn
MF/UF
$0.75bn
Buildings
$0.75bn
Ozone/BAC
$0.65bn
UV-AOP
$0.48bn
Residuals
$0.45bn
Chemicals
$0.22bn

Sub-process splits are estimated from comparable California DPR programmes; the PWSC programme has not published a public itemised breakdown.

Annual operating cost (~$415M / yr, range $300–500M)

dominated by energy, membranes, chemicals, staffing

Sources: PWSC program material; Napa DPR feasibility study (Carollo); comparable California IPR/DPR engineering studies. Figures are indicative mid-points within published ranges.

Comparison

Advanced treatment costs benchmarked.

Cost per m³/day of installed capacity, by unit process, for the two California reuse programmes. Different scales — Napa at 10 MGD, PWSC at 150 MGD — yet the per-process unit costs land in remarkably similar territory. Reverse osmosis and membrane pretreatment dominate in both.

Napa — 10 MGD DPR
PWSC — 150 MGD IPR
$ per m³/day of capacity

Reverse Osmosis (RO)

Napa
$1,929
PWSC
$1,937

Microfiltration / Ultrafiltration (MF/UF)

Napa
$1,242
PWSC
$1,320

Buildings

Napa
$887
PWSC
$1,320

Ozone / Biological Activated Carbon (BAC)

Napanot used in this design
PWSC
$1,144

Ultraviolet Disinfection / Advanced Oxidation (UV / UV-AOP)

Napa
$819
PWSC
$845

Residuals

Napa
$634
PWSC
$792

Chemicals

Napa
$740
PWSC
$387

Napa figures from the District's Potable Reuse Feasibility Study (Carollo). PWSC per-process figures derived by dividing indicative treatment line items ($bn) by 568,000 m³/d nameplate capacity. Both breakdowns are best-available estimates; sub-process splits are not publicly itemised by either programme.

Part 2 — Levellised cost per m³ of delivered water

The price the water actually sells for — for comparison.

All-in cost per cubic metre once finance and operations are spread over delivered volume. The three Californian potable reuse projects sit at the top. Beneath them, nine Saudi independent sewage treatment plant tariffs show what competitively procured non-potable reuse costs at scale. Two recent large seawater desalination plants anchor the bottom of the chart.

$0.00
$0.50
$1.00
$1.50
$2.00
$2.50
$3.00

California potable reuse

  • Pure Water Southern California

    150 MGD · IPR · $2,900/AF

    $2.35
  • Napa Alt 3

    10 MGD · DPR/TWA · $3,000/AF

    $2.43
  • Napa Alt 6

    10 MGD · DPR/RWA · $3,200/AF

    $2.59

Saudi Arabia — non-potable reuse (ISTP tariffs)

  • Jeddah Airport 2

    2019 · no conveyance

    $0.24
  • Taif

    2019 · no conveyance

    $0.29
  • Madinah 3

    2021 · no conveyance

    $0.32
  • Dammam West

    2019 · no conveyance

    $0.34
  • Arana

    2025 · 41 km conveyance

    $0.36
  • Buraydah 2

    2021 · no conveyance

    $0.38
  • Tabuk 2

    2021 · no conveyance

    $0.38
  • Al-Haer

    2023 · 32 km conveyance

    $0.52
  • Hadda

    2025 · 38 km conveyance

    $0.63

Large seawater desalination

  • Soreq II

    Israel · 548,000 m³/d · PPA

    $0.41
  • Hassyan

    Dubai · 818,000 m³/d · PPA

    $0.37

What the comparison shows

  • Californian potable reuse delivers water at $2.35–$2.59 per m³. Large modern seawater desalination delivers it at $0.37–$0.41 — roughly six times cheaper.
  • Saudi Arabia's competitively-procured non-potable reuse plants land in the same band as desalination, at $0.24–$0.63 per m³. Treatment to irrigation rather than potable spec, large scale, and competitive PPP procurement do most of the work.
  • Within the Saudi cluster, the three most expensive projects (Al-Haer, Hadda, Arana) all include long-distance conveyance — 32 to 41 km. The six cheapest have no conveyance burden at all. Even on a 30¢/m³ baseline, getting the water from where it's made to where it's used adds real cost.
  • Years of competitive price discovery in the Middle East desalination market give us a very clear idea of what the price of desalination should be. We are still a long way from understanding what the cost of reuse should be.

PWSC: MWD lifecycle unit cost, 150 MGD, 100% debt at 4% over 30 years. Napa: Carollo feasibility study (2024), 12-month operation. SWRO and Saudi ISTP figures are published 25-year PPA / BOT tariffs at preferred bidder award.

Sources: MWD official programme material; Napa Purified Water Feasibility Study; GWI DesalData; Saudi Water Partnership Company tender data.

The economics page so far has been about cost. But cost is only half the picture. Whether a project gets built — and whether the water it produces commands a price that covers its cost — depends just as much on what the water is worth to whoever uses it. And reused water is not all the same product. A litre delivered to a farm and a litre delivered to a chip fab are valued in entirely different worlds.

The value of water

A cubic metre of water is not a cubic metre of water.

What reused water is worth depends entirely on what it replaces or supplies. Water to irrigate a hectare of farmland and water to feed a semiconductor fabrication line are both, literally, cubic metres of H₂O. Their economic value differs by a factor of fifty or more. Migrating reuse capacity towards higher-value applications is one of the two main ways to improve the economics of reuse.

$0$1$2$3$4$5US$ per m³ of water deliveredIndustrial process watere.g. cooling, boiler feed, wash, product$0.80$5+Potabledirect and indirect$0.50$5+Irrigationagricultural, landscape$0$0.40Other non-potableurban, street cleaning, toilet flush$0$0.20Environmentstream flows, wetlands, recreation$0$0.10The top of the industrial range is fifty times the top of the irrigation range.
  • Industrial process water is the most valuable on average. The low end of the industrial range ($0.80) is already above the high end of irrigation ($0.40). It reflects the fact that industrial users need a higher quality of water than agricultural water users.
  • The value of water is always a function of the alternatives. Communities which can source raw water for potable use for less than $0.50 per m³ are unlikely to consider a potable reuse project.
  • Most of today's reuse capacity is supplied at the bottom of the value scale. Irrigation, environmental flows, and other non-potable uses dominate the global reuse mix — and almost none of it is paid for at anywhere near the price reflected here. Most reclaimed water is supplied free of charge to farmers.

Value ranges represent typical willingness-to-pay and avoided-cost benchmarks across each application class. Within each range, value varies substantially by location, alternative supply costs, and end-user characteristics.

Source: GWI analysis; industry benchmarks.

Both sides of the economic ledger can move. Cost can come down — through innovation, scale, and smarter procurement. Value can go up — through migrating capacity towards higher-value applications and through reforming how water is priced. The two levers don't pull against each other; they pull together. The next section is about how.

Changing the economics

How do we change the economics of water reuse?

  • Scale

    Reuse is still a cottage industry, with each project feeling like the first of its kind. As the industry scales, projects will become more standardised and easily replicated. There will also be more economies in the production of the basic components of the treatment train. That is why we call this the Scaling Reuse Initiative.

  • Innovation

    Water reuse projects involve a huge range of treatment processes, all of which can be improved to bring down the cost of reuse. Ensuring that the R&D community is focused on the right challenges is what our Tech Innovators Working Group is all about.

  • Public attitudes

    A huge amount of the cost of water reuse arises from the fact that the public is unfamiliar with it and concerned about the potential risks. We need to turn the argument around so that reuse is welcomed as the most sustainable source of water. That is part of what our Cities, Utilities and Communications Working Group is tasked with doing.

  • Regulation

    The value of reuse is very much a function of regulation. Under-regulation creates unnecessary obstacles to reuse projects, while over-regulation can make them prohibitively expensive. Our Policy and Regulation Working Group aims to promote fit-for-purpose enabling regulation for water reuse.

  • Finance

    Water reuse has a double or triple value proposition: wastewater treatment, product water sales, and energy/materials recovery. It should be an excellent investment. Our Finance Working Group is dedicated to opening up that opportunity and developing easily replicable models.

  • Industry

    The most valuable opportunity in water reuse is probably in partnerships between industrial water users and municipal wastewater utilities. We need to unlock this potential by bringing the two sides together. That is part of the purpose of our Industry & Supply Chain Working Group. The other part is exploring and promoting best practice in on-site reuse so that it is as widely adopted as possible.

You can read more about our working groups here.